Project:
Diagnostic Imaging Centre Fit-out
Client:
Imaging at Olympic Park
Architect:
JDA Architects
Project Manager:
Clare McBeath
Contract Details:
Delivered via a fixed price lump sum after competitive tender.
Cost:
$1,978,316.00
Management Structure:
Project manager: Chris Bato
Site Supervisor: Neil Pickard
|
|
Building Works:
Fit-out of imaging facility including preparations for installation of an MRI Machine, a CT Scanner, General X-Ray, Ultrasound and Fluoroscopy. A Reception area and waiting room with a 'living' Phyto plant wall was also installed along with the required change rooms and restroom facilities.
Site Specific Building Solutions:
This project had a very strict and tight timeline to work within. Whilst also having the added challenge of the major construction works still going on around us. Very good, very clear communication and co-ordination was needed and a commitment from our staff and subcontractors to work together was imperative to the successful completion of the work.
Contract Results:
Building works were completed to the satisfaction of the client, in a timely manner. Additional work requests along the way meant the timeline became even tighter. DNAco communicated at length with the client to fulfil the needs of the project successfully.